This is where it all started, on a hillside overlooking Hwy.
377 at the new Knox Ranch development in
Granbury, Texas
Crews began harvesting the stone from the surrounding
property in mid-February, 2009
We have used more than 200 truck-loads of stone in the
construction of Veteran Falls
Excavation began on April 20, 2009.  The large excavator
was provided by Holt Cat and other large equipment and
labor provided by J.W. Hughes Excavation
In no time at all, the falls begins to take shape.  You
can get an idea of the scale by looking at the people and
equipment toward the top of the falls.
Once the excavation was completed, Oilfield Plastics
installed the liner.  This went in in sections that had
to be fused together on-site.
The moment we have all been waiting for...the first
stone is set.  Notice the scrap liner and cushion sand
that is underneath the stone.  This happens for every
stone set in the project.
Once several stones are set, you start to see the
layering and the different levels of the falls.  The center
of this canyon is where the water will flow.
Another milestone for the project.  The pumps have
arrived from Munro Pumps...and they are impressive!
The two pumps will move over 180,000 gallons of water
per hour, creating massive whitewater on the falls.  
Pump stands constructed by J.W. Hughes Excavation
Justice Plumbing installed hundreds of feet of 12 inch
pipe to carry the water to the top of the falls.  The
massive water pressure is releaved by branching the
12" pipe into two 16" discharge pipes at the top.
The massive stones are set in place with the use of
these large cranes, provided by Hurd Crane.  Without
them, it would be next to impossible to accomplish
anything in this scale.
The large concrete culverts were provided and
installed by Hanson Pipe and Precast.  Once
assembled, this created an underground waterway.
The crew works to cover the culverts and create a
natural walkway across the water feature.  
This shows the walkway area, over the underground
waterway, once it has been brought back to a natural
look.   Once the plants mature, it will look as if it has
always been there.
The area in the center, about one third of the entire
width,  is where the water will flow.  You can see how
much wider the feature was excavated and lined.  This
type of waterfall is made up of multiple layers of  stone,
to achieve the whitewater effect that is so desirable.
This stone is one of several that is being set in place to create small caverns at the mouth of
the cave where the water will go underground.  In the background you can see the many layers
of stone that create the face of the waterfall.  
Crew members work on some of the small detail work
that is so critical to the success of this water feature.  
One of the finished edges & patio area on the right.
Robert Stapleton and crew began to harvest stone
hill at knox ranch
Robert Stapleton harvested 0ver 200 semi loads of stone.
Robert Stapleton watches as excavation of Veteran Falls begins
Robert Stapleton's crew working on excavation of Veteran Falls
Robert Stapleton works with Oilfield Plastics to line Veteran Falls
Robert Stapleton works with the crew as the first stone is set at Veteran Falls
Robert Stapleton and crew work to create the layers of Veteran Falls
Robert Stapleton examines one of two pumps for Veteran Falls
Robert Stapleton inspecting pipes iinstalled by Justice Plumbing for Veteran Falls
Robert Stapleton works with Hurd Crane to set the massive stones at Veteran Falls
Robert Stapleton works with Hanson Pipe and Precast at Veteran Falls
Robert Stapleton and crew naturalize a section of Veteran Falls
Robert Stapleton created a natural environment at Veteran Falls
Robert Stapleton and crew work on Veteran Falls
Robert Stapleton and Crew work on Veteran Falls
Robert Stapleton  and crew set a large stone into place in Veteran Falls
Construction History of Veteran Falls
The following pictorial history shows the order of the different steps of the construction of the
Veteran Falls Memorial.  The waterfall is 290 feet long and 70 feet wide.  We have used over 220
semi-truck loads of stone, each and every one of them pulled from the surrounding property.

The liner, provided and installed by Oilfield Plastics, using over 28,000 square feet of liner.  The
two 20 horsepower pumps, supplied by Munro Pump Company, will move 180,000 gallons of
water, per hour.  The pipe that carries the water from the bottom pond to the top of the
waterfall is 12' diameter PVC, provided and installed by Justice Plumbing.  At the top of the
falls, the pipe splits off into two, 16' outlets.  There is also a third pump that will be installed in
the top of the waterfall to produce a geyser.

All the stone for the project were harvested from the surrounding 2100 acres.  To date, 220 semi
loads of stone have been placed, the largest stone weighing over 35,000 lbs.
Robert Stapleton designer and creator of Veteran Falls
This artist's rendering shows what the completed
waterfall will look like.  Notice the geyser at the top.  
(This picture was created using actual photographs of
the project.  Only the water was added for effect.)
Robert Stapleton oversees construction of Veteran Falls
Robert Stapleton orgainzes crews for Veteran Falls construction
The crew from J.W. Hughes Excavation were experts in
working with the large equipment.  They operated them
like they were an extension of their own bodies.
The large equipment from Holt Cat allowed us to fly
through the excavation process.  Great machines, great
service, great company.
Robert Stapleton coordiinated with G & G Electric on the Veteran Falls project
With all the heavy equipment churning the soil, it
became very dusty.  We were able to manage it with the
use of this water truck from Holt Cat.
G & G Electric, Inc. pulls all the wire that will be
needed to power the massive pumps for this project.
801 Seale Street           Dallas, TX 75208             214-403-1407              veteranfalls@yahoo.com